Name
of the Stage |
Approvals |
1 |
Stage-0 Project Identification |
|
Executing Agency will be required to receive approval on Project Concept Note from line Ministry |
|
EA will be required to obtain final approval on PPP projects from CCEA for PICOM Listing |
|
2 |
Stage-1 Feasibility |
|
EA will be required to obtain necessary consents from line ministry to engage consultant for Feasibility study. |
 |
EA will need to obtain final approval on feasibility study report and its proposed major terms and conditions from the line ministry/CCEA |
|
3 |
Stage-2 Commercial Framework |
 |
EA will be required to obtain necessary consents from line ministry ;to engage Transaction Consultant |
 |
EA will be required to obtain approval of pre-qualification documents and issuance from Line Ministry |
 |
EA\LM approval to release invitation for EOI notice |
|
Approval of PTEC evaluated report on PQ by Line Ministry |
|
Approval of Finalized bid documents and issuance of IFT by Line Ministry |
|
4 |
Stage-3 Evaluation
of Tender |
|
Approval of PTEC Bid Evaluation Report by Ministry/EA |
|
Government approval of successful tenderer |
|
Issue Letter of Intent by |
|
EA/Procuring Entity |
|
5 |
Stage-4 Negotiation |
 |
EA will be required to take all necessary consents to Form Government negotiating Team |
 |
EA will take necessary legal consents on final Concessionaire agreement from Law Ministry |
 |
Final Approval of security package to be signed by LM/EA |
 |
Government approval For Sign Agreement with Project Company |
|
6 |
Stage-5 Financing |
 |
Project Company will be required to obtain consents on Financial Closure from Lenders |
|
7 |
Stage-6 Construction |
 |
Project Company will be required to obtain Site Clearance Certificate from Department of Environment to go for construction |
 |
Approval of Environment Impact Assessment report from DOE |
|
Consents required from EA for satisfactory completion test |
|